Google
กก

Home | Product | Solution |Purchase | contract-us

กก
กก
Design requirements

    

1 Overview
1.1 In order to ensure the compatibility of the second phase system, in the same system, the contractor should use the same manufacturers
The equipment and software. The above requirements apply to the following system:
a) transmission system
b) a dedicated telephone system
c) the public service telephone system
d) recording system
e) Visual intercom system
1.2 engineered a second phase should be to meet with the networking and unified operation and management.
1.3 within 30 days of the entry into force of the contract, the contractor must submit design plans for approval. Design plans should be
A list of lists, including the following
a) the delivery of file directory and file a brief description;
b) each item on the list of planned date of submission and approval of the situation. List in the monthly progress
Report to be updated;
c) Outline of the preparation of progress and in accordance with section 1.4 and 1.5 requirements.
1.4 plan for each project should have a clear date for the progress. The plan required monthly progress reports
Update. Provisions in various stages of process to the engineers time to submit documents and information to prepare for Progressive
Degree of monitoring and / or approval.
1.5 formalities in accordance with the contractor to submit these documents. All documents with a document number should be issued on
Period, a modified version as well as all amendments to records.
1.6 shall be submitted to the system outlined in the statute, the specific requirements, see "technical specifications" Volume II "special requirements"
And third volumes of "Appendix."
1.7 the preliminary design stage, including (but not limited to) the following:
a) an initial system composed of the layout of display systems, the Internet, site locations and related information
b) preliminary design calculations to confirm the effectiveness of the preliminary design is scheduled to meet the needs and requirements of available
c) equipment and cable and design specifications to meet regulatory requirements
d) power consumption and heat estimates
 
The first book dedicated special requirements specification
37
e) Electromagnetic Compatibility Plan
f) software requirements specification
g) a detailed interface specification (DIS) the first draft of
h) software testing and confirmation of the plan
i) system operation plan to demonstrate that they meet the operational and functional requirements
1.8 the design phase of the medium-term include (but are not limited to) the following:
a) a detailed layout and configuration of the system
b) detailed design calculations
c) the steps in detail
d) software design specifications
e) Software Test Description
f) Link Agreement
g) the installation design, including equipment installation design, installation instructions, wiring and cross-site
Goods, of civil, building equipment and the installation of information ABWF
h) to submit a model, the contractor should be designed in the mid-principle approval has been submitted before the 24-week sample
Board.
1.9 final design phase, including (but not limited to) the following:
a) install the maps and records
b) the installation program (including cable installation instructions, installation of major equipment, and other systems
Interface work, etc.)
c) maintenance plan
2 to install maps and records (the final design stage)
2.1 required to submit plans to complete the installation engineer for approval. Completion of the installation plan should include the following parts:
a) System Settings Chart
b) Schematic
c) equipment and associated cable layout routing
d) fiber optic cable, cable and the introduction of follow-up, distribution and use of cored wire diagram
 
The first book dedicated special requirements specification
38
e) layout of the indoor equipment
f) layout of equipment racks
g) power distribution and access map
h) the installation of equipment specific details
Figure 2.2 System Settings should show details of various systems, including systems interface type, quantity, equipment
And cable connections.
2.3 diagram should show the device name, type, routing and connectivity equipment cable terminations, including a complete end -
Client description, such as pins and cable distribution of the color code.
2.4 The layout of equipment should show in detail the location of equipment, cable installation, including installation details and cable routes
By.
2.5 cable, cable and the introduction of follow-up, distribution and use of cored wire map should show the introduction of trunk optical cable stations,
OCC method of space communications equipment, follow-up process, the name of loop distribution.
2.6 Layout of equipment racks and other indoor equipment layout should be shown all the equipment name, location and size.
2.7 Electricity distribution and access map should show the name of the distributor, the type, location, and cables, grounding of an
Loaded way. Need to explicitly specify the use of power, the fuse every way cable / circuit breaker / isolation switch
And requirements specified value.

Related Product:

       

กก